One small step for foundation walls, one giant leap for the addition to Regina Hall! Our project continues to make great progress. Now that all of the foundation walls are completely done, we look forward to getting this building up and out of the ground. We will be setting structural steel and pre-cast in the week to come.

The Past Weeks

Finished all footings

Finished all foundation wall pours

Chipped into bed rock to excavate for elevator pit

Waterproofed the exterior of foundation walls

NAMI started under floor plumbing

Landscape work finished on south end sidewalk

 

Coming  Up... 

Deliver and set structural steel

Deliver and set pre-cast

Finish under floor plumbing

Slab-on-grey pour