Construction Update - Late September 2015

  • Monday, Sep 28, 2015

What's New

The addtion to Regina Hall has come a long way in the past few weeks. Now that the 1st and 2nd floor wall panels are set it is easier to see the shape of the building. The air handling unit has been lowered into the lower level and setr in place, with duct work and piping to follow.Work coninues in the days ahead to set 3rd floor panels. When crews complete this step, they will beging to set roof trusses.

 

 

 

 

 

 

The Past Weeks

  • Set wall panels on first and second floor
  • Completed welding on metal deck on second floor
  • Finished concrete topping on first floor
  • Backfilled all of the addition's foundation
  • Set air handling unit in place

Coming up...

  • Set the remaining second and third floor wall panels
  • Place roof trusses and plywood 
  • Install storm sewer system