Construction Update - October 2015

  • Tuesday, Oct 13, 2015

What's New

Great progress continues on the new residence hall project. All the interior and exterior structural wall panels have been installed. The heating, ventilation, and air conditioning (HVAC) crew has work underway with the installation of duct work and piping in the lower level. Installation of the roof trusses is nearly complete, and is ready for wood work. Once the prep work for the trusses is complete, crews will beging installing shingles. Masons will begin exterior brickwork while the roofing is completed.  

The Past Weeks

  • Finished 3rd floor wall panels and decking
  • Set roof trusses in place
  • HVAC crew work underway
  • Fire hydrant was relocated, and connected to water main
  • Waterproofing exterior walls underway

 

The Weeks Ahead

  • Install plywood on roof
  • Set metal decking and pour concrete for upper floor
  • Begin brick work for exterior walls