Construction Update - Late January 2016

  • Monday, Jan 25, 2016

What’s New?

We have kept the ball rolling here at the site. Drywall and painting is has been completed on the lower level. We’ll now move to the ceiling grid next.

On the second floor drywall and taping continues. First floor ceiling drywall begins soon, and taping will follow that.

Mechanical rough-ins are being installed on the third floor. Most of the windows for the west entry curtainwall have been installed.

 

 

 

 

 

The Past Weeks

  • Completed painting on lower level
  • Installed west entry curtainwall
  • 1st floor ceiling drywall
  • 2nd floor drywall taping
  • 3rd floor mechanical rough-in

Coming Up in the Weeks Ahead

  • Drywall on and 3rd
  • Start painting 2nd
  • Ceiling grid on lower level
  • Install lower level diffusers, lights and sprinklers
  • Exterior siding and more soffits