Construction Update - Late March 2016

  • Monday, Apr 11, 2016

What's New?

Significant progress continues on the Regina Hall Expansion project. Bathroom sinks, tiles, toilets, and flooring have been added on the lower two levels. Elevator equipment is on site and preparation for installation is underway. Outside, work on the exterior ramp wall is underway. 

The Past Weeks

  • Vinyl flooring for lower level and first floor installed.
  • Installed wood doors on second and third floors.
  • Ongoing painting of third floor.
  • Installed kitchen cabinets on second and third floors.

In The Weeks Ahead

  • Install site walls and sidewalks.
  • Installation of elevator.
  • Installation of bathroom partitions.
  • Installation of carpet for lower level and first floor.